PBA achieved major victories during the RAC review and adoption of the 2021 IRC base code for the most recent PA UCC update that will be effective for building permit applications starting on July 13, 2025, with a 6-month phase in date of January 13, 2026.

Estimated reduction in costs to construct and base code compliant home range from $12,000 to $18,000 based upon the Department of Energy model house.  The actual reduction will vary based upon the square footage, foundation style, climate zone, and a host of other factors.

Use this as a guide to understand PBA member benefits.  These values do not include other past victories from previous code update cycles that were legislative or did not change from previous RAC modifications / deletions such as sprinkler mandate, stair geometry, electrical changes, wall bracing, and many more.

Major Victories for Builders in the PA UCC Adoption of the 2021 ICC Model Codes

Structure and Planning:

R310.1- Emergency escape and rescue opening required.

  • Created a new exception for in-fill properties in areas such as Philadelphia
  • Allows previously non-compliant properties to comply
    • Properties with in-fill lots that are sprinklered in accordance with Section 2904, and a minimum clear yard size of 80 sq ft (7.43 m2) shall, be allowed to have access to the public way provided by a shared easement that is a minimum of 30 in (762 mm) wide.

 

R506.2.3 – Vapor retarder.

  • Deletes the 2021 requirement for the under-slab vapor barrier to be an ASTM E1745 compliant Class A, 10-mil product
  • Remains as the current 6-mil vapor barrier

 

R703.2 – Water-resistive barrier.

  • Codifies that the WRB layer can serve as the Air Barrier in accordance with Chapter 11 requirements
  • This was subject to interpretation in the past and the language was updated in the 2024 IRC.
  • The new added language mirrors this change:
    • Where the water-resistive barrier also functions as a component of a continuous air barrier, the water-resistive barrier shall be installed as an air barrier in accordance with Section N1102.4.1.1.

Plumbing:

P2905.3 – Hot water supply to fixtures.

  • This new section was not adopted
  • Would have required the built-up length of hot water pipe from the hot water source to the farthest fixture to be a maximum of 100’
    • No need to create a calculation for submission with the building permit application demonstrating compliance
    • No need to field verify that the length is 100’ or less
    • No need to try to centralize HWH or bathroom groupings giving more design flexibility to meet customer needs
    • No need to add an additional HWH or a recirculation system when compliance cannot be achieved without these costly options

Electrical:

E3601.8 – Emergency disconnects

  • This is a new section that requires Emergency disconnects to be installed on the exterior of all homes along with labeling requirements
  • Language was changed to limit the requirement to Detached homes
    • For one- and two-family detached dwelling units, all service conductors shall terminate in disconnecting means …
  • This allows Attached homes to eliminate this requirement
    • Duplex units may be subject to interpretation from the code official since they are considered attached dwelling units

 

E3901.4.2 – Island and peninsular countertops and work spaces

  • Island and Peninsular countertop area outlets
  • The modified language in this section was not adopted and will remain the current requirements of at least 1 receptacle outlet
  • Revised language would have required:
    • At least one receptacle outlet shall be provided for the first 9 square feet (0.84 m2), or fraction thereof, of the countertop or work surface. A receptacle outlet shall be provided for every additional 18 square feet (1.7 m2), or fraction thereof, of the countertop or work surface
      • Receptacles would still need to be in compliant locations to be counted
        • not under an overhang or more than 6”
        • 2 receptacles located next to each other on a compliant side would only count as 1 location
        • Could be a pop-up located on the countertop

 

E3905.8 – Boxes at fan outlets

  • Modifies the new language to eliminate the subjective interpretation for Paddle Fan box locations
    • Outlet boxes mounted in the ceilings of habitable rooms in a location acceptable for the installation of a ceiling-suspended (paddle) fan shall comply with one of the following:
  • The 2021 IRC language using the phrase “in a location acceptable” created interpretation in neighboring states that required the proper box and bracing for multiple locations in a room
  • The modified language requires the fan box and bracing for locations where a paddle fan is being installed
    • Locations that are for ceiling fixtures (not noted as paddle fans) will be able to utilize the proper boxes and bracing for lights or other installations (such as wifi extenders) without meeting the paddle fan requirements

 

Energy: 

Figure N1101.7 and Table N1101.7 – Climate zones

  • The new climate zone maps (matching ASHRAE) and county listings were adopted in the 2021 Chapter 11 as written
    • Changes PA to be only 2 climate zones (CZ4 and CZ5)
      • All CZ6 counties are now CZ5
      • Some CZ5 counties became CZ4
        • Adams, Berks, Cumberland, Dauphin, Franklin, Lancaster, Lebanon and Perry

 

N1101.13.5 – Additional energy efficiency

  • This new section was not adopted
  • This would have required the inclusion of an Additional Energy Efficiency package to be chosen in addition to the remaining prescriptive sections
    • If choosing the prescriptive path for compliance, you will not need to also choose an optional package to meet the requirements of this Chapter 11

 

Table N1102.1.3 – R-Value alternative

  • Insulation values were greatly changed to be similar to the current values
    • CZ5 counties that moved to CZ4 will see a benefit
    • CZ5 counties that remain as CZ5 will see a small increase in values
    • Refer to separate chart to see the changes for each Climate Zone

 

N1103.3.5 – Duct testing

  • The updated 2021 section was not adopted as it relates to homes where all ducts and equipment are located in conditioned spaces
  • The updated section would have required Duct Leakage testing regardless of the location of equipment and ductwork

 

N1103.3.7 – Building cavities

  • This was not adopted keeping PA at the currently adopted 2009 language
  • Allows the use of Joist Bays and Stud Cavities for return air plenums as permitted by the Mechanical chapters of the IRC
    • Make sure if your system will utilize this design that any notation related to this section is removed from the architectural plans -or- have a note inserted on the plan that allows for return air plenums per Mechanical chapter

 

N1104.1 – Lighting equipment

  • This was not adopted keeping PA at the current language of 90% high efficacy lighting
  • New language would have required 100% of all lighting thus making some lighting fixtures that come with self-contained bulbs non-compliant

 

N1104.2 – Interior lighting controls

  • This new section was not adopted
  • This section would have required occupancy sensors or dimmers in most rooms that contain permanently installed lighting

 

N1104.3 – Exterior lighting controls

  • This new section was not adopted
  • This section would have required special lighting controls and resets once the total wattage of exterior lighting exceeded 30 watts

 

N1108.1 & N1108.2 – Additional efficiency package options

  • These sections were modified by removing the requirement of N1101.13.5 that was not adopted, thus making this an option not a requirement
    • 1 (R408.1) Scope. This section establishes additional efficiency package options to achieve additional energy efficiency.
    • Section N1108.2 (R408.2) Additional efficiency package options. Additional efficiency package options are set forth in Sections N1108.2.1 (R408.2.1) through N1108.2.5 (R408.2.5).